What It Takes to Set Up AWP Software on a Project

3 min read · Updated Oct 2026

Setting up AWP software starts in FEED, before engineering produces its first package. The software is selected there, alongside the AWP strategy, the construction work areas (CWAs), a preliminary path of construction, and the data requirements. After that, the software depends on structures agreed in advance, data loaded on a fixed cadence, and people who know how to run it.

The Structures Agreed Before Engineering Packages

Before engineering develops its first engineering work package (EWP), these are in place:

The software is configured to these structures. Renaming packages or changing the hierarchy after data is loaded means changing every system that references them, and how Primavera P6 carries an AWP program shows why those shared IDs matter.

The Data, Loaded on a Cadence

Engineering loads its packages into the AWP software, including the documents, the material takeoffs with fabricator piece marks, and every form of model, from engineering and structural to vendor, fabricator, and spool files. Conditioned models arrive weekly. Packages change only through the package register, the AWP software is aligned after each register issue, and a monthly review reconciles it with the schedule and the document register.

The Model

Model components link to tags and packages through attributes set in the design model, such as CWA, CWP, and EWP. Model conditioning for AWP covers what those attributes need. A project without a usable model can still start, and AWP without a 3D model covers what changes.

The People

The setup step most often skipped is dedicated, full-time AWP and information management leadership from FEED or sanction, with responsibilities set in a RACI. Training runs from the start for everyone who touches the packages, soft crafts and vendors included.

How openAWP Is Set Up

openAWP can start a project from its AWP Standard template, with the tables, tabs, and relationships already set up and nothing in it locked. Tables and fields change without code. Data loads from Excel, Primavera P6, data warehouses, and other connected systems, on a schedule or on demand. An engineer from our team works with you on the setup and is billed hourly, and the software itself has no license fee.

Our AWP consulting team writes the procedures and the package structure the software runs on.

Related Articles

What Is Advanced Work Packaging?

A plain-language definition of AWP, why capital projects use it, and how it changes execution planning.

7 min read

How Workface Planning Fits Into Advanced Work Packaging

Workface planning is the last step in AWP, turning engineered scope into packages a crew can execute.

5 min read

Advanced Work Packaging Without a 3D Model

What the 3D model does in a full AWP procedure, what still works when a project has no usable model, and which controls have to be rebuilt by hand.

4 min read

Self-Hosted AWP Software with P6 and Power BI

What self-hosting AWP software means for project data, how it divides work with the Primavera P6 schedule, and how Power BI reads package data from it.

4 min read

Which Project Phases AWP Software Should Cover

What AWP software should hold from FEED to turnover, covering the path of construction, EWPs and PWPs, IWPs and the lookahead, testing, and system completion.

4 min read

How the AWP Package Hierarchy Maps to Software

The eleven AWP package types from CWA to SWP, who owns each one, and the rules AWP software has to hold for parents, one-to-one packages, and the register.

3 min read

How to Evaluate Advanced Work Packaging Software

Seven areas to evaluate in AWP software, drawn from what an AWP procedure asks of it, from building IWPs from the model to completing work by system.

3 min read

How Advanced Work Packaging Software Is Priced

The three parts of AWP software cost, which are the license, the setup, and support through execution, and what each one covers on a capital project.

3 min read

AWP for Brownfield Projects and Turnarounds

How advanced work packaging applies inside an operating plant, from the existing plant in the model and site-controlled drawings to MOC and turnarounds.

3 min read

How Owners Run AWP Across Several EPC Contractors

How an owner runs AWP across several EPC contractors with a standard set before contracts are signed, owner roles, one naming convention, data, and audits.

3 min read

What Model Conditioning Is and Why AWP Needs It

What model conditioning covers, from attributes per the data requirements and CWP volumes to an EWP-structured tree, tag checks, and vetted vendor models.

3 min read

See How openAWP Supports Advanced Work Packaging

Explore the product these articles are about, or book a live demo to see it on your own project.