How the AWP Package Hierarchy Maps to Software

3 min read · Updated Oct 2026

The AWP package hierarchy maps to software as linked records, with one table per package type, each record pointing to the one it belongs to, and one controlled register of how the packages relate. The Construction Industry Institute (CII) describes AWP as developing constraint-free work packages aligned to an optimized path of construction, and a full AWP procedure expands its core levels into eleven package types, each with one owner and one definition.

The Package Types

PackageWhat it isOwner
CWAA geographic area of the plot, all disciplinesEngineering, with construction input
CWPOne discipline inside one CWA, defined by a 3D envelope, sized for one general foreman for 6 to 8 weeksConstruction contractor
EWPAll engineering information for one CWP, which is its documents, model, and MTOEngineering contractor
VEWPVendor engineering needed for one CWP, managed as attributesEngineering, with vendors
FEWPFabricator engineering for its parent EWPFabricator
PWPThe material data for one CWP against its required-on-site dateEngineering contractor
FPWPA fabricator's shop package feeding exactly one CWPFabricator
MWPLoad, ship, and set of a module at siteModule fabricator
IWPConstraint-free work for one foreman and crew for 7 to 10 days, from one CWPConstruction contractor
TWPTesting work, linked to IWPs by line numberConstruction contractor
SWPAll remaining work for one system, for turnoverConstruction contractor

The Rules Software Has to Hold

No package is created, split, or merged outside that register. How Primavera P6 carries an AWP program covers how the same structure appears in the schedule.

Where the Levels Live

CWAs sit at Level 2 of the schedule, packages at Level 3 as real activities of about eight weeks, and IWPs at Level 4 in the AWP software, never in the Level 3 schedule.

How openAWP Maps It

openAWP supports the full hierarchy, with each package type as its own table and a single parent reference on each record, so everything above a record is derived. Its AWP Standard template starts a project with that structure, and every field in it can be changed.

Our AWP consulting team writes AWP procedures and the package structure behind them.

Related Articles

What Is Advanced Work Packaging?

A plain-language definition of AWP, why capital projects use it, and how it changes execution planning.

7 min read

How Workface Planning Fits Into Advanced Work Packaging

Workface planning is the last step in AWP, turning engineered scope into packages a crew can execute.

5 min read

Advanced Work Packaging Without a 3D Model

What the 3D model does in a full AWP procedure, what still works when a project has no usable model, and which controls have to be rebuilt by hand.

4 min read

Self-Hosted AWP Software with P6 and Power BI

What self-hosting AWP software means for project data, how it divides work with the Primavera P6 schedule, and how Power BI reads package data from it.

4 min read

Which Project Phases AWP Software Should Cover

What AWP software should hold from FEED to turnover, covering the path of construction, EWPs and PWPs, IWPs and the lookahead, testing, and system completion.

4 min read

What It Takes to Set Up AWP Software on a Project

How AWP software is set up from FEED, with the structures agreed before engineering packages, data loaded every week, the model link, and full-time leadership.

3 min read

How to Evaluate Advanced Work Packaging Software

Seven areas to evaluate in AWP software, drawn from what an AWP procedure asks of it, from building IWPs from the model to completing work by system.

3 min read

How Advanced Work Packaging Software Is Priced

The three parts of AWP software cost, which are the license, the setup, and support through execution, and what each one covers on a capital project.

3 min read

AWP for Brownfield Projects and Turnarounds

How advanced work packaging applies inside an operating plant, from the existing plant in the model and site-controlled drawings to MOC and turnarounds.

3 min read

How Owners Run AWP Across Several EPC Contractors

How an owner runs AWP across several EPC contractors with a standard set before contracts are signed, owner roles, one naming convention, data, and audits.

3 min read

What Model Conditioning Is and Why AWP Needs It

What model conditioning covers, from attributes per the data requirements and CWP volumes to an EWP-structured tree, tag checks, and vetted vendor models.

3 min read