Which Project Phases AWP Software Should Cover

4 min read · Updated Oct 2026

AWP software should cover the project from FEED to system turnover. The AWP strategy, construction work areas (CWAs), a preliminary path of construction, the data requirements, and the software itself are all set during FEED, and the package method then runs unchanged until the last system is accepted. Software that only tracks construction leaves engineering, procurement, and completions to spreadsheets.

FEED and the Path of Construction

CWAs come first, then the path of construction, which is the optimal building sequence expressed as a dated sequence of construction work packages (CWPs) in the Level 3 schedule. It is agreed in weekly Interactive Planning sessions with engineering, procurement, construction, operations, and commissioning at the table. The software holds the CWAs, the CWP list, and the register of package relationships. What advanced work packaging is covers why the plan runs backward from startup.

Engineering and Procurement

Each CWP determines the scope and need dates of its engineering work package (EWP) and procurement work package (PWP), one to one. The software tracks them against those dates.

Material readiness covers the procurement side.

Construction and the Workface

CWPs are dissected into installation work packages (IWPs), each one foreman and crew for 7 to 10 days, released only when constraint-free. IWPs live at Level 4 in the AWP software, inside the 4 Week Look Ahead, and never in the Level 3 schedule. Workface planning covers the daily rhythm.

Testing and Completion

Testing runs through test work packages (TWPs), linked to IWPs by line number. As construction passes set progress gates, the work shifts from areas to systems. At 70% the lookahead is re-sequenced to the turnover order, and at 75 to 80% (or 90 days before the commissioning need date) the remaining work is packaged into system work packages (SWPs). Each SWP holds all remaining work for one system, with real hours, and the method stays the same to the last punch item.

How openAWP Covers the Phases

openAWP holds the phases in one set of linked tables for CWAs, CWPs, EWPs, IWPs, tags, constraints, and systems. Progress uses weighted milestones that work for engineering, procurement, fabrication, and commissioning as well as installation, and completions roll up from tags to systems.

Setting up AWP across every phase of a project? Our AWP consulting team builds the structure and the procedures.

Related Articles

What Is Advanced Work Packaging?

A plain-language definition of AWP, why capital projects use it, and how it changes execution planning.

7 min read

How Workface Planning Fits Into Advanced Work Packaging

Workface planning is the last step in AWP, turning engineered scope into packages a crew can execute.

5 min read

Advanced Work Packaging Without a 3D Model

What the 3D model does in a full AWP procedure, what still works when a project has no usable model, and which controls have to be rebuilt by hand.

4 min read

Self-Hosted AWP Software with P6 and Power BI

What self-hosting AWP software means for project data, how it divides work with the Primavera P6 schedule, and how Power BI reads package data from it.

4 min read

What It Takes to Set Up AWP Software on a Project

How AWP software is set up from FEED, with the structures agreed before engineering packages, data loaded every week, the model link, and full-time leadership.

3 min read

How the AWP Package Hierarchy Maps to Software

The eleven AWP package types from CWA to SWP, who owns each one, and the rules AWP software has to hold for parents, one-to-one packages, and the register.

3 min read

How to Evaluate Advanced Work Packaging Software

Seven areas to evaluate in AWP software, drawn from what an AWP procedure asks of it, from building IWPs from the model to completing work by system.

3 min read

How Advanced Work Packaging Software Is Priced

The three parts of AWP software cost, which are the license, the setup, and support through execution, and what each one covers on a capital project.

3 min read

AWP for Brownfield Projects and Turnarounds

How advanced work packaging applies inside an operating plant, from the existing plant in the model and site-controlled drawings to MOC and turnarounds.

3 min read

How Owners Run AWP Across Several EPC Contractors

How an owner runs AWP across several EPC contractors with a standard set before contracts are signed, owner roles, one naming convention, data, and audits.

3 min read

What Model Conditioning Is and Why AWP Needs It

What model conditioning covers, from attributes per the data requirements and CWP volumes to an EWP-structured tree, tag checks, and vetted vendor models.

3 min read

See How openAWP Supports Advanced Work Packaging

Explore the product these articles are about, or book a live demo to see it on your own project.